Chilled Water Storage Checking Procedures

Policy

Testing of chilled water, boiler water and cooling tower water is conducted on a monthly basis by Contractor under the direction of Central Plant.

Procedures

Responsible PersonAction
Contractor
  • Conducts testing of all chilled water, boiler water and cooling tower water each month.
  • Submits reports/documentation to Central Plant Office.
Central Plant Technicians
  • File and retain documentation in Central Plant office.

Date created:
January 2005

Approved by:

Senior Technician, Central Plant

Previous edits:

Responsible:

Senior Technician, Central Plant

Date for review:

January 2006

File reference:

F7549

Previous titles: