Chilled Water Storage Checking Procedures
PolicyTesting of chilled water, boiler water and cooling tower water is conducted on a monthly basis by Contractor under the direction of Central Plant. Procedures| Responsible Person | Action | | Contractor | - Conducts testing of all chilled water, boiler water and cooling tower water each month.
- Submits reports/documentation to Central Plant Office.
| | Central Plant Technicians | - File and retain documentation in Central Plant office.
|
|